The Financial Exposure Behind AI Infrastructure

Company filings from Atlas Energy Solutions, NET Power and SoftBank show how data-centre projects carry borrowing, equipment commitments, conditional reimbursements and procurement losses before generating revenue.

A modular data centre connected to the electricity grid. Photo: Samirshah23, Wikimedia Commons, CC BY-SA 4.0. https://creativecommons.org/licenses/by-sa/4.0/

An AI data centre can carry substantial financial obligations before it begins selling computing capacity.

Developers may have borrowed against customer arrangements, ordered generation equipment, paid supplier advances or assumed construction costs while the project is still years from operation.

Recent filings from Atlas Energy Solutions, NET Power and SoftBank show how those obligations appear in company disclosures.

Atlas Energy Solutions: project borrowing and equipment commitments

On 22 October 2026, Atlas Energy Solutions ProjectCo entered into a bridge credit facility with an initial commitment of $424 million. It drew approximately $171.2 million at closing.

The agreement allows for up to a further $286 million in financing, subject to lender consent and additional conditions. That amount is not part of the initial committed facility.

The borrowing supports two power projects, each covered by a Customer Reimbursement Agreement (CRA) with the same unnamed customer.

These agreements provide for reimbursement of specified project costs. They do not, on the information disclosed, establish that the projects have secured all the long-term revenue or financing required for completion.

The loan has an initial maturity of 180 days.

ProjectCo may obtain one 184-day extension, provided it meets specified conditions.

These include executing two customer energy supply agreements in a form acceptable to the lenders and obtaining lender consent.

The supply agreements are described as future requirements; the filings do not identify them as executed contracts.

The reimbursement arrangements are also tied directly to loan repayment. Customer reimbursement receipts and certain equipment-related recoveries must be applied to prepay the facility.

ProjectCo cannot terminate either CRA unless the remaining reimbursement obligations are sufficient to cover outstanding principal, interest and fees.

Each loan draw requires supporting documentation and certification concerning customer approval, equipment eligibility and the remaining reimbursement limits.

The facility carries interest at 2.50% over SOFR, rising to 3.00% over SOFR six months after the effective date.

ProjectCo also pays an annual fee of 0.50% on undrawn commitments and a duration fee equal to 0.50% of aggregate commitments on each six-month anniversary while loans remain outstanding.

The borrowing sits alongside substantial equipment procurement obligations.

Atlas disclosed a 1.4 GW Caterpillar Global Framework Agreement with an initial aggregate purchase obligation of approximately $840 million.

A separate WMC generator purchase agreement carries an estimated additional commitment of $67.2 million and may satisfy part of the Caterpillar obligation, subject to confirmation.

Atlas also reported an estimated $309.4 million remaining commitment under a WMC balance-of-plant agreement, after applying an earlier reservation agreement.

These figures cannot simply be added together.
The WMC generator agreement may cover part of the Caterpillar obligation, while the balance-of-plant agreement covers a different equipment and services scope.

The Caterpillar framework runs through 2030 and is based on monthly demand forecasts.
Atlas reported no spending against it as of 30 September 2026.

Other project-specific arrangements create additional procurement exposure.

A November 2025 reservation agreement covered approximately 240 MW of generation equipment at an aggregate cost of $278.3 million. A related engineering, procurement and construction agreement added an estimated $53.7 million for balance-of-plant equipment and labour.

By 30 September, Atlas had spent $280.3 million against these commitments, leaving $51.7 million outstanding. It reported a further $2.7 million in spending after quarter-end.

The company also disclosed several other purchase commitments. One, for power equipment, totalled $43.1 million, of which $4.4 million had been spent and $38.7 million remained outstanding at 30 September.

A further $8.6 million was spent after quarter-end. Another commitment stood at $220.2 million, with no spending recorded at quarter-end and $33 million spent subsequently. A separate $27.9 million commitment, for equipment expected to be delivered in 2028, also had no spending recorded at 30 September.

Atlas links these obligations to separate customer reimbursement arrangements. They therefore need to be assessed by project and contract rather than treated as one consolidated procurement bill.

The supplier contracts also matter if a project is cancelled. Under the WMC balance-of-plant agreement, Shackelford can terminate all or part of an order for convenience on 14 days’ notice.

Termination does not eliminate the payment obligation: Atlas must pay amounts already due and WMC’s documented cancellation costs, together with reasonable internal costs, overhead and profit attributable to work performed. WMC is also required to mitigate those costs.

The bridge facility is secured by substantially all assets of the borrower and certain subsidiaries, alongside a pledge of the borrower’s equity.

Atlas Energy Solutions Inc. provides a parent guarantee described as unsecured. Some related-party reimbursement amounts for equipment funded by affiliates before the loan closed are redacted.

The public disclosures establish the facility’s headline terms and several significant procurement obligations, but leave important contractual details unavailable.

The complete CRAs, the contemplated energy supply agreements, the full security documents and the supplier contracts have not been disclosed.

That leaves uncertainty around customer approval rights, reimbursement caps, supplier cancellation charges and the obligations that would survive a project termination. The potential financial loss in a cancellation or customer-withdrawal scenario cannot therefore be calculated from the public filings alone.


NET Power: acquisition and construction obligations without a binding offtake agreement.

On 31 August 2026, NET Power acquired EMPower's position as owner under an engineering, procurement and construction (EPC) agreement with Saulsbury Industries.

The project is a 123 MW natural-gas power facility intended to supply a co-located data centre.

The transaction involved approximately $117.6 million in acquisition costs and equipment-related payments.

At 30 September, approximately $119.1 million remained payable under the EPC agreement, including a mobilisation payment of about $10.2 million.

If NET Power issued the full notice to proceed on its then-current schedule, about $88.2 million would become payable over the following 12 months.

These amounts depend on contractual milestones and could change under the post-closing change order, including adjustments for relocation, suspension, storage and price escalation.

A separate equipment supply agreement could create a further payment obligation.

If the EPC agreement is terminated, NET Power may elect, subject to specified conditions, to take assignment of the related equipment contract and assume approximately $23.3 million in remaining payments.

Termination alone does not trigger that amount; the obligation depends on NET Power taking the assignment.

NET Power also has a cost reimbursement agreement with a prospective data-centre customer.

If no energy services agreement is signed by 14 February 2027, or certain other specified events occur, the customer may take assignment of covered equipment and contracts and reimburse approved non-refundable costs.

If it declines assignment, the agreement provides for reimbursement of qualifying costs and certain resale losses, unless NET Power elects to retain the equipment.

Payments are subject to a cap of approximately $180 million, expense eligibility and other contractual conditions.

At the third-quarter reporting date, no amount had become payable under the agreement and NET Power had recognised no reimbursement receivable.

The cap does not provide committed project financing or guarantee recovery of all expenditure.

At the time of the third-quarter filing, NET Power had not signed a binding energy services or power offtake agreement with the prospective customer.

The customer was not obliged to enter one. The reimbursement agreement therefore did not provide a committed revenue stream or the funding required to complete the project.

NET Power would still need project financing, equipment financing, equity, partner capital or another source of funds.

Construction had been suspended since 1 July 2026.

Resuming the full EPC scope required a full notice to proceed, the mobilisation payment and satisfaction of other conditions, including reviews by Saulsbury and Wärtsilä.
During the suspension, NET Power remained responsible for specified standby, preservation and storage charges, subject to negotiated limits.

A filing on 23 November extended the deadline to 4 December for executing the Fourth Amendment and limited notice to proceed and making the required payments.

Saulsbury had not demanded the $3.5 million termination payment, which was not then payable; it remained deferred under the extension.

The 8-K also identifies 31 March 2027 as the deadline for delivering the full notice to proceed and funding the mobilisation payment. NET Power reported that the prospective customer had approved the form of the Fourth Amendment subject to conditions.

The filing did not announce a binding energy services or power offtake agreement.

NET Power's disclosed exposure therefore includes acquisition costs already incurred, EPC payments dependent on project progression, possible equipment-contract payments if it takes assignment, and charges associated with continued suspension or termination.

The customer agreement may reimburse some eligible costs. It does not remove the need to finance construction or ensure that every cost will be recovered.

SoftBank: procurement losses recognised in reported results

Silver Bands 7 (SB7), in which SoftBank Group and SoftBank Vision Fund 2 have invested, made cumulative payments of ¥1.500886 trillion ($9.48 billion) on the relevant procurement from the previous fiscal year through 30 September 2026.

That is not the amount written off. SoftBank recognised a six-month loss of ¥597.248 billion ($3.73 billion): ¥457.030 billion in non-refundable advances and ¥140.218 billion in contract modifications and settlements.

SoftBank also disclosed conditional future rebates of up to $2.1 billion on equipment purchases.

It recognised no asset for those potential rebates. They are not current cash recoveries and cannot be deducted from the reported procurement loss.

A separate impairment of ¥72.543 billion related to a Lordstown manufacturing facility.

It is distinct from the Silver Bands 7 procurement loss and should not be attributed to the same arrangements.

SoftBank attributed the procurement revision to changes in the requirements of existing and planned projects.

The disclosure records a loss from the revised arrangements; it does not establish that every affected project was cancelled or that all cumulative procurement payments were lost.

SoftBank's presentation does not include the underlying supplier contracts or a complete allocation of the Silver Bands 7 exposure among the investors and counterparties.

The public figures therefore do not show which parties ultimately bear each component of the loss.

Financing across the advanced-computing buildout

The Federal Reserve's November 2026 Financial Stability Report places these company disclosures within a much larger expansion of financing for advanced-computing infrastructure.

The report estimated that debt issuance associated with advanced computing had exceeded $680 billion by October 2026. It also estimated more than $1.1 trillion in outstanding public debt related to advanced computing.

Separately, the report's 2026 second-quarter comparison put the undiscounted value of leases not yet commenced above $1 trillion and guarantees and contract commitments above $2 trillion.

The latter category includes take-or-pay contracts and residual-value guarantees. These figures relate to a different reporting period from the October debt estimates and should not be added to debt as though they were equivalent liabilities.

The estimates rely on public disclosures and do not capture every private financing arrangement.

The Federal Reserve describes how large technology companies support third-party data-centre developers through long-term capacity leases, which developers can use to secure construction financing.

It also notes that GPU manufacturers may guarantee residual values to support equipment purchases.

These arrangements can create financial links between highly rated technology firms and smaller developers without appearing as conventional borrowing by the developer alone.

What the public disclosures do not establish

This analysis covers selected public disclosures available through 24 November 2026. Atlas, NET Power and SoftBank are not a representative sample of the entire AI infrastructure market, and their reported amounts cannot be combined into a market-wide estimate.

The evidence is incomplete in different ways. Some amounts appear in financial statements; other terms are redacted or contained in agreements that are not publicly available.

An undisclosed liability cannot be assumed to be zero. Conversely, a maximum reimbursement cap or purchase framework is not evidence that the full amount has been spent or is unconditionally payable.

A fuller assessment would require the underlying customer and supplier agreements, financing documents, termination provisions and conditions governing reimbursement or assignment.

It would also require following amendments to those contracts as each project moves from procurement through construction and into operation.

Continue exploring

Follow the idea further.

Explore more reporting and analysis from across the Resonance archive.

More on Markets & FinanceBrowse selected reading

Continue reading

Recommended from the archive

Wholesale gold bars stacked on a pallet inside a secure vault
Markets & Finance

Can Money Work Without Debt?

Modern money is closely tied to bank lending, but does economic growth require debt-created money? A look at credit, fixed supply and the lessons of the gold standard.

Read article
Markets & Finance

The SEC Opened Path for Onchain Stock AMMs After Clarity Act Failure.

Here’s What Changed.

Read article
Markets & Finance

LAST WEEK IN CRYPTO

Bitcoin Squeezes to $81K Then Gets Marked Down by Jackson Hole, Solana Passes Its First Binding Governance Vote, and a Cronos Oracle Attack Forces a Chain Halt

Read article